Remodeling Change Orders and What to Review Before Approving Extra Work

A remodel is underway, and a decision changes. You want a different fixture, an unavailable product needs a substitute, or demolition reveals a condition that could not be confirmed earlier. What happens next should be understandable before anyone treats the new work as approved.

A written change order records an agreed change to the project. For a homeowner, its value is practical: it connects the reason for the change with the work, price and schedule consequences. A clear process helps you decide without losing track of what was already included.

Start with the original agreement

Keep the signed contract, scope, drawings and selection list together. A proposed change should identify the part of those documents it affects. If the original scope says a wall will be painted, a request to complete that painting is different from asking to add paneling to the same wall.

When something is presented as extra, ask where the original scope ends and the proposed addition begins. Do not assume every unexpected conversation creates an added charge, or that every newly discovered condition was included in the original price. The facts and your agreement matter.

If you disagree about responsibility, document the question and ask for the relevant contract provision and scope detail. For a significant contract dispute, get qualified independent advice. A general planning article cannot determine either party’s rights in a particular project.

Identify why the change is proposed

Different reasons call for different decisions. An owner-requested upgrade may be optional. A product substitution may be necessary to keep a selection workable. A concealed condition may require investigation before anyone can define the repair.

Ask for a plain-language explanation and photographs where useful. Which part is confirmed, and which part still needs evaluation? What alternatives are available? If you decline an optional improvement, can the original work continue as planned?

Keep a discovery separate from a finished repair proposal. Finding damage does not, by itself, tell you the full extent of work. Ask how the team will establish that extent and report back before presenting a final solution.

Make the description specific enough to check

A useful change description names the room or location, the work being added or removed, the product or finish where relevant, and any drawing revisions. It also identifies what remains unchanged.

For example, a hypothetical change from one vanity to another should identify the replacement model and explain whether plumbing connections, countertop dimensions, wall repair or delivery arrangements change. The phrase upgrade vanity leaves too much room for different expectations.

If the new work depends on another decision, record that dependency. A pending countertop selection or unresolved fixture dimension should not disappear inside a broad description that sounds final.

Review the net price including credits

Ask for the total adjustment under the contract’s pricing method. The document should make clear whether it adds to or reduces the contract amount. Discuss applicable materials, labor, delivery, tax and other charges rather than focusing only on the replacement item’s retail price.

When work or products are removed, ask how any credit is calculated. Ordered materials, return conditions and work already performed can affect the answer. Do not assume the entire original amount disappears, but do ask for an explanation you can follow.

An allowance adjustment should identify the allowance being reconciled so you can see what is already carried in the contract. Confirm that the same cost is not being counted both as a new charge and as an unchanged allowance.

Ask what the change does to the sequence

Price and time are separate questions. A substitute product might cost less but arrive later. A design revision might require another measurement, drawing update or inspection step. Ask which activities are affected and what schedule assumption is being used.

Have the contractor explain whether other work can continue while the decision is made. Do not assume the entire project must stop, or that the change has no effect because installation takes only a short time. Ordering and coordination can matter as much as the visible work.

Include household consequences in your own decision. If the change extends the time without a kitchen or bathroom, update your temporary living plan before approving an optional addition.

Use one approval channel

Washington L&I’s Hire Smart guidance recommends putting changes to materials or scope in writing and avoiding verbal amendments. Agree at the beginning of the project on who can authorize changes and how that approval is recorded.

A conversation with a worker should not leave the household wondering whether something has been ordered. Send requests through the designated project contact and ask for the complete change document. If more than one homeowner is involved, coordinate your decision before sending conflicting instructions.

Discuss the procedure for urgent protective action before an emergency occurs. The contract should explain how those situations are handled; do not invent a blanket approval rule in the middle of a problem.

Maintain a running change log

Give each proposed change a number, date and status such as proposed, approved, declined or superseded. Save the signed version and mark earlier versions clearly so an outdated option is not mistaken for the current instruction.

Track the original contract amount, approved increases, approved credits and revised total. Keep payments and the remaining balance separate from that scope total. Review the log with the project contact periodically, especially before a major purchase or final accounting.

For an upcoming remodeling project, contact Broussard Construction at (360) 509-0280 or phillip@broussard-homes.com. Ask to discuss the scope and change process together so you know how decisions will be handled once work begins.

Washington contractor registration: BROUSHS858KO.

Share Article

Our Recent Articles

Remodeling Change Orders and What to Review Before Approving Extra Work

A remodel is underway, and a decision changes. You want a different fixture, an unavailable product needs a substitute, or demolition reveals a condition that could not be confirmed earlier. What happens next should be understandable before anyone treats the new work as approved. A written change order records an

Choosing Flooring for a Pacific Northwest Home Beyond the Sample Board

A flooring sample tells you about color and texture. It says much less about the floor underneath it, the doorway it must meet or how it will handle your household’s routine. Those details can determine whether a material that looks right is a sensible choice for a particular room. In

Can You Live at Home During a Remodel? Make a Room-by-Room Plan

Staying home during a remodel sounds simple until the room being rebuilt is also the route to your only bathroom. Whether the arrangement is workable depends on the project, the household and how the work area can be separated from daily life. Decide with a room-by-room plan rather than a

Frequently Asked Questions

The initial site visit and estimate are free!

Yes, we offer in-house financing. Contact us to learn more.

Each project will have a payment schedule that will coincide with specific project milestones. Payment schedules are broken down into three payments; deposit, progress payment, and final. For projects under $2,000, the payment will be collected in full after the project has been completed. We accept checks, cashier checks, and all major credit/debit cards.

Yes! Contact us to learn more.